Dec 03, 2025
Client: New Energy Battery Technology Company, Wuhan, China
Objective: Upgrade and expand facility MEP systems to support dry rooms, secondary sealing zones, and electrolyte preparation areas.
Scope: Comprehensive installation and commissioning of dehumidification, chilled water, compressed air, vacuum, argon piping, process utilities, and electrical systems.
The client required modernization of key production areas to ensure precise environmental control, reliable process utilities, and compliance with safety standards. Systems had to support uninterrupted production and integrate with existing infrastructure.
| System / Area | Scope & Description |
|---|---|
| Structural & Rooms | Demolition and modification of dry rooms, electrolyte prep, and secondary sealing zones; ceiling, partitions, lighting adjustments. |
| Process Pipelines | Compressed air, vacuum, argon, and exhaust piping; integration with firefighting and drainage systems. |
| Dehumidification & Cooling | Dehumidifiers, chillers, cooling towers, circulation pumps; stainless-steel welded ducts in dry areas. |
| Electrical & Control Systems | Cable trays, power distribution, equipment wiring, and control circuits; automated monitoring and safety interlocks. |
| Installation & Commissioning | Full MEP installation, flushing, pressure testing, trial runs, and commissioning per national standards. |
Stable environmental conditions in dry rooms and secondary sealing zones
Reliable chilled water and compressed air supply for production processes
Improved energy efficiency and automation for reduced manual intervention
Compliance with national safety and fire protection standards


October 26, 2016
The Most Successful Engineering ContractorApr 21, 2025
Mexico - Clean Environment SolutionApr 21, 2025
Serbia - Clean Environment SolutionsApr 21, 2025
LeeKr Technology - Cleanroom Environment Solutions